The Currency Rounding that Benefited Odebrecht

A solitary block of concrete, barely protected from flood by sump pumps, lies in the waters of the lower Caroní River. This is the case of the planned Manuel Piar hydroelectric plant in Tocoma, southern Venezuela, after paying US$ 10 billion —three times the budget and partly with funds from multilateral agencies— to several contractors, including the controversial Brazilian construction company. Of that amount, at least US$ 1 billion corresponded to irregularly paid foreign currencies through an administrative scheme (80-20, they called it) that an internal audit found, which was used to finance commissions to project management.

11 June 2017

"The '80 -20' must not be known; otherwise, the Tocoma project falls," warned one engineer to another in the middle of the urgency to progress with the works (once again) of the Manuel Piar hydroelectric plant, in Tocoma, Bolivar state, in the rich Venezuelan Guayana. It was 2014, and the internal auditors of Corpoelec, the Venezuelan state power holding company, had months of reviewing the work's invoices - including many issued by the Brazilian company Odebrecht - to find out the reasons for its delay and the great escalation of its cost.

In Ciudad Guayana, the industrial and commercial capital of the region, the "80-20" was an open secret. Engineers, technicians, administrators, trade unionists and lawyers working there knew that billing in bolivars had been dollarized through this mechanism that contravened the exchange control and the initial contract.

"Tocoma was, at least from 2009 to 2014, a big petty cash," said an engineer who worked on the dam. It was profitable for many. The initial cost of Tocoma was estimated at US$ 3.9 billion. Seven years later, in 2014, Venezuela had paid nearly US$ 10 billion, partly with loans from the Andean Development Corporation (CAF) and the Inter-American Development Bank (IDB). What happened?

Consulted sources indicate that its initial cost had been increased by rampant inflation, constant modifications required by Corpoelec and surcharges by contractors, but mainly because of a "comparative advantage" that Venezuela offered to foreign and national entrepreneurs in relation to the rest of the world, which blinded more than the gold of Guayana: the exchange control that gave rise to the secret audited by the audit of Corpoelec.

More than Engineering: Financial Prestidigitation

The Tocoma hydroelectric plant, the works of which started in 2007, scheduled to run from 2012, was mostly carried out by Odebrecht. Due to its size and cost, it was one of the largest hydroelectric infrastructure projects in the country and in Latin America, comparable in cost and magnitude to the expansion of the Panama Canal. A million and a half cubic meters (52,972,000.08 cubic feet) of concrete were emptied in the place.

Where there should be ten turbines generating electricity, bilge pumps work instead

Today, the block of concrete deteriorates day by day, and in the vaults intended for ten electricity generating turbines, bilge pumps work so that the waters of the lower Caroní River do not flood the few installed power systems through some cracks in its walls.

In parallel, it is known that the Prosecutor's Office silently investigates Odebrecht's irregularities in the country and the Government negotiates the project close with contractors. After being questioned by the National Assembly, neither the civil works contractor OIV consortium (made up of Brazil’s Odebrecht, Italy’s Impregio and Venezuela’s Vinccler), nor the electromechanical works contractor, Argentina’s Impsa (of the problematic group Pescarmona), explained why the works stopped. They did not answer a questionnaire sent to include answers in this report either.

From 2007 to 2012, Venezuela was in full oil boom. The original engineering plans for the work were modified by the government, which began to demand more expensive supplies, increase the payroll of workers without disregard (from 2,000 to 10,000), and force its "opening" by sections, due to political reasons. The new requirements increased year by year the cost of the work.

Corpoelec – due to non clarified reasons - started delaying payments to contractors, which were to be in bolivars and U.S. dollars under contract, depending on the component payable. Private companies faced the increase in prices in bolivars for salaries and products, and the beginning of a shortage of industrial inputs that had to be purchased in the country. "Neither cement nor rebars could be bought in the country," recalls a former construction engineer. "There were also no spare parts available," recalls another.

In 2010, in a meeting between OIV (led by Odebrecht) and Corpoelec, they discuss the effect of the constant changes to the contract and the demand for new materials and machinery. The consortium presents a claim to the government: "The initial prices fell short, the exchange control limits me, I charge peanuts in U.S. dollars and a lot in bolivars, I am spending more dollars than usual with your new demands." This is the line of argument of the contractors.

The aim was to increase payment in dollars (cheap) and lower the component payable in bolivars

The solution came as a percentage: 80-20. The aim was to increase payment in dollars (cheap) and lower the component payable in bolivars. It worked like that from 2010 to 2014. Corpoelec converted the amount in U.S. dollars of OIV's bill into bolivars at the preferential exchange rate (4.30). Then it was added to the bill in bolivars. The total was broken down into two parts, 80% and 20%. The first amount was converted into dollars at a preferential rate, and the second was in bolivars. Thus, an invoice of Bs. 2.3 billion and US$ 18.8 million became one of Bs. 491 million bolivars and US$ 456.9 million. "Over 1,000 bills were like this," says an Odebrecht engineer.

This 80-20 system was entered into between the parties in Addendum 4A of the contract, according to consulted sources, during the management of the then Minister of Electric Power Alí Rodríguez Araque. A consultation by email to the current ambassador in Cuba was not answered to the date of publication of this article. "Addendum 4A exists and provides for it. The accounts in Tocoma do not match because of this," says an Odebrecht engineer.

PRESENTACIO´N TOCOMA A JUNTA INTERVENTORIA 11-03-14 R3 (SUPERVISORY BOARD TOCOMA PRESENTATION 03-11-14) by ArmandoInfo on Scribd


There was apprehension between the middle management and Corpoelec project engineers. "Everyone knew that that would allow more rip-off," recalls another engineer. "But the top said that it would be signed. Chavez was pressing on Corpoelec. There were elections and a lot of money. " The contracted staff feared for their work if the anti-Pareto law transcended.
On that scheme, OIV charged and Corpoelec paid price increases, bonuses on meeting work completion dates, and valuations. "More than a thousand bills were paid like this," restate one of the current workers. The pecuniary losses were calculated internally. "US$ 1 billion were paid in that way, a good part in commissions for the Tocoma project management," he added.

Engineers —some still active in Corpoelec, others already outside— do not stop showing their astonishment that Tocoma has cost almost twice the expansion of the Panama Canal (5.4 billion U.S. dollars), or almost four of the cost paid by the country in dollars for the construction of a similar hydroelectric plant, Caruachi, very close to Tocoma, on the bed of the Caroní River.

In the Tocoma equation, x was always equal to extra payments in U.S. dollars

From 2007 to 2014, Tocoma experienced peaks and drops in the work rhythm. Corpoelec ‘s desperate response in several occasions —for electoral reasons, as the 2012 presidential elections— was paying for "speed-ups" that would not allow the opening as scheduled anyway.

The management of the Minister of Electric Power Jesse Chacón ran into a standstill of the work in 2013. And in reviewing the causes, a commission of auditors from Corpoelec found the exchange scam in July of that year. Its members warned the board of directors about the irregularity, suggesting that it was linked to an exchange crime in the hands of Corpoelec’s Engineering Management of Proyectos de Expansión Generación Oriente (expansion and power generation Project).

For example, they identified two bills for 363 million and 226 million payable in bolivars for works carried out in the country. Thus, they found that these and other conversions were made "without taking into account the current exchange regulations and the opinion of the corresponding legal instances" and "without having prior authorization for such change". Even so, those bills were later restructured and paid mostly in U.S. dollars, an Odebrecht engineer said.

The procedure with the 80-20 system was a pattern, they say. "The Audit Committee highlights the recurrence by Edelca (the state electric power company of the Caroní river) and Corpoelec in agreeing payments in foreign currency with the OIV Tocoma Consortium considering that the works are estimated to be carried out in the national territory," for a total of US$ 635,991,233.19. Payments made in the country, should be paid in bolivars only, under the contract.

Memo Auditoria OIV (OIV Audit Memo) by ArmandoInfo on Scribd

Alarmed, the auditors went to the legal consultancy to analyze the case. In August 2013, consultant Alejandro Carrasco gave his opinion: "The Engineering Management of Proyectos de Expansión Generación Oriente has been misinterpreting the way of converting to payment in U.S. dollars 80% of the amount of the valuation of work executed in foreign currencies and 20% in Bolivars corresponding to the same valuation, which should be corrected ".

In the document, Carrasco mentioned the limits contemplated by the Central Bank's law for the payment of projects in foreign currencies, according to the exchange agreements. The lawyer confirmed that he had studied the case and that the procedure was not in accordance with the initial contract.

Other courtesies for the contractors

In addition to the 80-20 system, the Auditors of Corpoelec found dozens of administrative irregularities, which they declared in several official reports, all revised for this report.

For example, Odebrecht, Impregilo and Vinccler obtained part of the contracts for additional (non-principal) work without bidding, in violation of the bidding law. They also received "overpayments", which affected Corpoelec's cash flow. They charged increases of up to 30% for claims without being approved by the appropriate authorities. They were paid, in some items, more than what was budgeted. They obtained month extensions for their work without submitting the mandatory supporting documentation.

For its part, Impsa, the Argentine contractor of the turbines, charged US$ 75 million from Corpoelec without having signed a contract. It also received US$ 60 million for equipment sent to the site; collected three million bolivars for labor costs that were not justified; assessed a tax at 3% instead of 34%; and it did not pay VAT. In addition, it signed a third contract without dating it, which is illegal. On one occasion it incurred in delays in the delivery of work, for which it had to pay 4.7 million U.S. dollars to Corpoelec in fines. There is no evidence that it has done it. In fact, only one and a half out of the 10 turbines that were paid are installed in Tocoma.

IDB and CAF were aware of these illegalities, sources say. Delegates attended the meetings of the board of the work periodically to verify progress against disbursements. However, they did not sign, as was appropriate, the modifications to the contracts and continued to finance the work, based on the audit. To the publication of this report, the requests for information sent by email to both institutions had not been answered.

¡Hola! Gracias por leer nuestro artículo.


A diferencia de muchos medios de comunicación digital, Armandoinfo no ha adoptado el modelo de subscripción para acceder a nuestro contenido. Nuestra misión es hacer periodismo de investigación sobre la situación en Venezuela y sacar a la luz lo que los poderosos no quieren que sepas. Por eso nos hemos ganado importantes premios como el Pulitzer por nuestros trabajos con los Papeles de Panamá y el premio Maria Moors Cabot otorgado por la Universidad de Columbia. 

Para poder continuar con esa misión, te pedimos que consideres hacer un aporte. El dinero servirá para financiar el trabajo investigativo de nuestros periodistas y mantener el sitio para que la verdad salga al aire.

ETIQUETAS:                    

Artículos Relacionados

Odebrecht's Masterpiece of Corruption worthy of an Art Gallery

Beyond the names of political figures and Government officials involved, the corruption plot deployed by the Brazilian construction company in Venezuela brought huge amounts of money in irregular payments into circulation. In Swiss banks, the transit of at least 235 million dollars was detected, mostly bribes linked to the Tocoma hydroelectric project, which after feeding the accounts of intermediaries reached their destination. For now, investigations determine that the capillarity through which the funds flowed led to art merchants, patriarchs of civil engineering dynasties, and even sports managers.

He who cuts the cake takes the biggest slice, learned the Viceroy of Odebrecht in Venezuela

Euzenando Azevedo had the doors of the Miraflores Palace open with Chávez and at the same time, he had a direct line with CEO Marcelo Odebrecht. Then, he became a key witness in the parade of plea bargains of the Lava Jato case. However, despite the many privileges, his testimony fell short. He failed to inform about some bank accounts in Switzerland that reveal that he kept money with one of the commissioners he had reported, Venezuelan lawyer Héctor Dáger.

03-06-18
Odebrecht Confessions

Kept under lock and key in Brazil since late 2016, the videos of the Odebrecht trial on Venezuela finally appear. As of today, Armando.info begins to publish a string of clips that show the faces of the witnesses who documented the case. Some of their statements had already been published on this platform, but here they go with the voice and tone of their protagonists.

Haiman El Troudi Has no One to Investigate Him

The judicial authorities of Switzerland found a connection between the wife and the mother-in-law of the former Venezuelan minister with at least 40 million dollars deposited in eight bank accounts, one of which was shared with one of the main negotiators of bribes and kickbacks between Odebrecht and the governments of Chávez and Maduro. Although they asked the Venezuelan justice to investigate the matter, the courts denied any possibility of addressing the case and the Venezuelan Prosecutor's Office, led by Tarek William Saab, acts as if not aware.

07-04-18
Chavez's Wishes to enter Mercosur were Odebrecht’s Commands  

Neither the revolutionary commander of Venezuela, nor the charismatic president Lula of Brazil, but the senior staff of the construction company turned into the Major Elector when the Brazilian Senate had to vote on the incorporation of Caracas into the trading bloc. Based on the transcripts of the Lava Jato case, Marcelo Odebrecht personally led the lobbying campaign aimed to break the three-year blockage that prevented the entry of the Chavista regime into the club. The operation included the recruitment of three key Senators from the Workers' Party, as allies.  

Odebrecht also Unites the Venezuelan Family

More than 550 million U.S. dollars went through the cliff in some Pdvsa Agrícola (PDVSA Agriculture) facilities, which were partly built in four provinces of Venezuela. A new file of judicial documents and bank deposits of the Lava Jato operation -leaked for this report- involve Egly Ramírez (uncle of the former president of the state oil company and current ambassador of Venezuela to the United Nations, Rafael Ramírez) and other former officials in the biggest corruption scandal of recent years that established a systematic payment of bribes to people with responsibilities in the governments of Latin America, so that the Brazilian multinational could win the tenders.

1 2 3

Otras historias

The 2019 blackout derived in a network in Mexico to evade sanctions against Maduro

When Vice President Delcy Rodríguez turned to a group of Mexican friends and partners to lessen the new electricity emergency in Venezuela, she laid the foundation stone of a shortcut through which Chavismo and its commercial allies have dodged the sanctions imposed by Washington on PDVSA’s exports of crude oil. Since then, with Alex Saab, Joaquín Leal and Alessandro Bazzoni as key figures, the circuit has spread to some thirty countries to trade other Venezuelan commodities. This is part of the revelations of this joint investigative series between the newspaper El País and Armando.info, developed from a leak of thousands of documents.

Lopez Obrador's government was aware of underground business with Venezuela

Leaked documents on Libre Abordo and the rest of the shady network that Joaquín Leal managed from Mexico, with tentacles reaching 30 countries, ―aimed to trade PDVSA crude oil and other raw materials that the Caracas regime needed to place in international markets in spite of the sanctions― show that the businessman claimed to have the approval of the Mexican government and supplies from Segalmex, an official entity. Beyond this smoking gun, there is evidence that Leal had privileged access to the vice foreign minister for Latin America and the Caribbean, Maximiliano Reyes.

Alex Saab left charcoal-marked fingerprints on Mexican network

The business structure that Alex Saab had registered in Turkey—revealed in 2018 in an article by Armando.info—was merely a false start for his plans to export Venezuelan coal. Almost simultaneously, the Colombian merchant made contact with his Mexican counterpart, Joaquín Leal, to plot a network that would not only market crude oil from Venezuelan state oil company PDVSA, as part of a maneuver to bypass the sanctions imposed by Washington, but would also take charge of a scheme to export coal from the mines of Zulia, in western Venezuela. The dirty play allowed that thousands of tons, valued in millions of dollars, ended up in ports in Mexico and Central America.

14-06-21
For everything else, there were Joaquín Leal and Alex Saab

As part of their business network based in Mexico, with one foot in Dubai, the two traders devised a way to replace the operation of the large international credit card franchises if they were to abandon the Venezuelan market because of Washington’s sanctions. The developed electronic payment system, “Paquete Alcance,” aimed to get hundreds of millions of dollars in remittances sent by expatriates and use them to finance purchases at CLAP stores.

Two stepbrothers — One penalty

Scions of different lineages of tycoons in Venezuela, Francisco D’Agostino and Eduardo Cisneros are non-blood relatives. They were also partners for a short time in Elemento Oil & Gas Ltd, a Malta-based company, over which the young Cisneros eventually took full ownership. Elemento was a protagonist in the secret network of Venezuelan crude oil marketing that Joaquín Leal activated from Mexico. However, when it came to imposing sanctions, Washington penalized D’Agostino only… Why?

They offered to resuscitate Venezuelan aluminum production but rescued a Mexican consortium

Through a company registered in Mexico – Consorcio Panamericano de Exportación – with no known trajectory or experience, Joaquín Leal made a daring proposal to the Venezuelan Guyana Corporation to “reactivate” the aluminum industry, paralyzed after March 2019 blackout. The business proposed to pay the power supply of state-owned companies in exchange for payment-in-kind with the metal.

1 2 3 24
Sitio espejo
usermagnifierchevron-down linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram